Title: Resolution to authorize the County Manager to execute an agreement for Guide Rail Replacements on portions of various County Roads with the lowest responsible bidder (EMI Guide Rail, LLC) for the replacement of approximately 10,000 feet of guide rail.

Narrative of Resolution:

title

Resolution to authorize the County Manager to execute an agreement for Guide Rail Replacements on portions of various County Roads with the lowest responsible bidder (EMI Guide Rail, LLC) for the replacement of approximately 10,000 feet of guide rail.

 

end

 

body

If Resolution requires expenditure of County Funds, provide the following information:

Amount to be authorized by Resolution: $966,636.00

Are funds already budgeted? Yes

Specify Compliance with Procurement Procedures:

B-24-16

RESOLUTION INTRODUCED BY PUBLIC WORKS COMMITTEE TO AUTHORIZE THE COUNTY MANAGER TO EXECUTE AN AGREEMENT FOR GUIDE RAIL REPLACEMENTS ON VARIOUS COUNTY ROADS

 

WHEREAS, bids were received for Guide Rail Replacements on various County Roads, and

 

WHEREAS, EMI Guide Rail, LLC, 693 River Road, Schenectady, New York 12306, is the lowest responsible bidder for this project, and

 

WHEREAS, the Sullivan County Division of Public Works has reviewed said bid and recommends that an agreement be executed.

 

NOW, THEREFORE, BE IT RESOLVED, that the County Manager be and hereby is authorized to execute an agreement with EMI Guide Rail, LLC, at a total price not to exceed $966,636.00 in accordance with B-24-16, said contract to be in such form as the County Attorney shall approve.