Resolution to authorize the County Manager to execute a contract change order with Holt Construction Corporation for Airport Terminal Project in the amount of $381,197.80, due to rock excavation expenses
end
body
If Resolution requires expenditure of County Funds, provide the following information:
Amount to be authorized by Resolution: $381,197.80
Are funds already budgeted? Yes
Specify Compliance with Procurement Procedures:
N/A
RESOLUTION INTRODUCED BY THE PUBLIC WORKS COMMITTEE TO AUTHORIZE THE COUNTY MANAGER TO EXECUTE A CHANGE ORDER WITH HOLT CONSTRUCTION CORPORATION FOR COSTS ASSOCIATED WITH ROCK EXCAVATION
WHEREAS, Resolution 463-23 adopted December 14, 2023 authorized an agreement with Holt Construction Corporation for construction of the airport terminal project in a contract amount of $19,005,023.00; and
WHEREAS, the agreement contained a unit price line item for rock excavation; and
WHEREAS, while excavating the basement area suspected rock was encountered and verified by the geotechnical engineer; and
WHEREAS, this same defined rock has been found throughout the building site at various depths; and
WHEREAS, rock excavation and associated concrete work has been required as a result of the defined rock; and
WHEREAS, the current estimate total for rock excavation and associated concrete work is $381,197.80, which was not included in the original construction contract amount.
NOW, THEREFORE, BE IT RESOLVED, that the County Legislature authorizes the amount of $381,197.80 to be paid to Holt Construction Corporation via a contract change order, bringing the contract amount to $19,386,220.80.