File #: ID-8865    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 11/13/2026 In control: Executive Committee
On agenda: 11/19/2026 Final action:
Enactment date: Enactment #:
Title: Amend Resolution No. 312-26 to reflect the correct “not to exceed” amount
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Narrative of Resolution:

title

Amend Resolution No. 312-26 to reflect the correct “not to exceed” amount

end

 

body

If Resolution requires expenditure of County Funds, provide the following information:

Amount to be authorized by Resolution: $0

Are funds already budgeted? Choose an item.

                     If ‘Yes,’ specify appropriation code(s): Click or tap here to enter text.

                     If ‘No,’ specify proposed source of funds: Click or tap here to enter text.

Specify Compliance with Procurement Procedures: Bid/ RFP & number:  R-22-29

RESOLUTION INTRODUCED BY THE EXECUTIVE COMMITTEE TO AMEND RESOLUTION 312-26 TO CORRECT TOTAL NOT TO EXCEED COST 

 

WHEREAS, Resolution 312-26 authorized the execution of a contract modification to adopt an updated rate schedule from H2M Architects, Engineers, Land Surveying and Landscape Architecture, D.P.C for Engineering Design Services for Redundant Potable Water Tank at the Human Service Complex; and

 

WHEREAS, this resolution incorrectly stated the amount not to exceed; and

 

WHEREAS, the correct not to exceed amount should be $155,875.00, due to a previous contract mod that increased the original total by $15,875.00, via resolution 126-25.

 

NOW, THEREFORE, BE IT RESOLVED, Resolution 312-26 is hereby modified as per the above.