File #: ID-5512    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/1/2023 In control: County Legislature
On agenda: 5/18/2023 Final action: 5/18/2023
Enactment date: 5/18/2023 Enactment #: 214-23
Title: Resolution to authorize the County Manager to execute a contract for the Repair of County Bridge 198.

Narrative of Resolution:

title

Resolution to authorize the County Manager to execute a contract for the Repair of County Bridge 198.

end

 

body

If Resolution requires expenditure of County Funds, provide the following information:

Amount to be authorized by Resolution: $286,140.00

Are funds already budgeted? Yes

Specify Compliance with Procurement Procedures:

B-23-27

RESOLUTION INTRODUCED BY THE PUBLIC WORKS COMMITTEE TO AUTHORIZE THE COUNTY MANAGER TO EXECUTE AN AGREEMENT WITH GREEN MEADOWS  INCORPORATED FOR THE REPAIR OF COUNTY BRIDGE NO. 198 (PROJECT).

 

WHEREAS, bid proposals were received for the Project to repair County Bridge 198, located on County Road 33, also known as Eldred-Yulan Road in the Town of Highland; and

 

WHEREAS, Green Meadows Incorporated, 1061 Plains Road, Wallkill, NY 12589, is the lowest responsible bidder; and

 

WHEREAS, the project is eligible for 100% State funding through the Bridge NY program; and

 

                     WHEREAS, the Division of Public Works has reviewed the bids and recommends award to Green Meadows Incorporated.

 