Narrative of Resolution:
title
Resolution to authorize the County Manager to execute a modification agreement with Delta Engineers for engineering services needed for the Repair of County Bridge 198
end
body
If Resolution requires expenditure of County Funds, provide the following information:
Amount to be authorized by Resolution: $16,500
Are funds already budgeted? Yes
Specify Compliance with Procurement Procedures: N/A RESOLUTION INTRODUCED BY PUBLIC WORKS COMMITTEE TO AUTHORIZE THE COUNTY MANAGER TO EXECUTE A MODIFICATION TO THE AGREEMENT FOR CONSULTANT ENGINEERING DESIGN AND RIGHT OF WAY INCIDENTAL AND CONSTRUCTION ENGINEERING SERVICES FOR THE BRIDGE NY COUNTY BRIDGE 198 REPLACEMENT PROJECT WITH DELTA ENGINEERS, ARCHITECTS & LAND SURVEYORS
WHEREAS, Resolution 36-19 authorized the agreement with Delta Engineers, Architects & Land Surveyors to provide engineering design and construction inspection services; for the Bridge 198 Replacement Project; and
WHEREAS, Resolution 161-22 authorized additional design and construction engineering services needed for the waterproofing of the bridge; and
WHEREAS, the bids for the construction of the waterproofing work came in higher than the budget requiring the project to be rebid; and
WHEREAS, additional engineering services were required to prepare documents for the rebidding of the waterproofing work; and
WHEREAS, the Division of Public Works recommends that a modification agreement be given to Delta Engineers, Architects & Land Surveyors for the additional work needed to prepare the rebidding documents.
NOW, THEREFORE, BE IT RESOLVED, that the County Manager is authorized to execute a Modification Agreement for consulting inspection and engineering services with Delta Engineers, Architects & Land Surveyors at a cost not to exceed $16,500, said contract to be in such form as the County Attorney shall approve.
end