Narrative of Resolution:
title
Resolution to authorize the County Manager to execute a Modification Agreement with H2M Architects, Engineers, Land Surveying and Landscape Architecture, DPW for additional scope of work for Redundant Potable Water Storage Tank at Human Service Complex.
end
body
If Resolution requires expenditure of County Funds, provide the following information:
Amount to be authorized by Resolution: $15,875.00
Are funds already budgeted? Yes
Specify Compliance with Procurement Procedures:
R-22-29
RESOLUTION INTRODUCED BY THE PUBLIC WORKS COMMITTEE TO AUTHORIZE THE COUNTY MANAGER TO EXECUTE A MODIFICATION AGREEMENT WITH H2M ARCHITECTS, ENGINEERS, LAND SURVEYING AND LANDSCAPE ARCHITECTURE, DPC FOR ENGINEERING DESIGN SERVICES FOR THE REDUNDANT POTABLE WATER STORAGE TANK AT THE HUMAN SERVICE COMPLEX
WHEREAS, Resolution No. 428-22, adopted October 20, 2022, authorized an agreement with H2M Architects, Engineers, Land Surveying and Landscape Architecture, DPC ("H2M") for engineering design services for the Redundant Potable Water Storage Tank at the Human Service Complex; and
WHEREAS, during the new tank design the existing controls and telemetry serving the existing tank, began to fail and due to their age replacement parts are not available; and
WHEREAS, the County requested H2M add the design of new controls and telemetry into their tank project design/bid documents scope of work; and
WHEREAS, the Division of Public Works requested a revised fee proposal from H2M to cover this additional scope of work, has reviewed the received proposal, and recommends the approval of a Modification Agreement.
NOW, THEREFORE, BE IT RESOLVED, that the County Manager is authorized to execute a Modification Agreement for additional engineering design services with, H2M Architects, Engineers, Land Surveying and Landscape Architecture, DPC, 5...