County of Sullivan header
File #: ID-6828    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 10/4/2024 In control: Public Works Committee
On agenda: 10/17/2024 Final action:
Enactment date: Enactment #:
Title: Resolution to authorize the County Manager to execute an agreement with NYSDOT to provide 95% funding for the Construction and Construction Support/Inspection work needed to replace County Bridge 82
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Narrative of Resolution:
title
Resolution to authorize the County Manager to execute an agreement with NYSDOT to provide 95% funding for the Construction and Construction Support/Inspection work needed to replace County Bridge 82
end

body
If Resolution requires expenditure of County Funds, provide the following information:
Amount to be authorized by Resolution: $5,784,284.00
Are funds already budgeted? Yes
Specify Compliance with Procurement Procedures:
N/A
RESOLUTION INTRODUCED BY PUBLIC WORKS COMMITTEE TO AUTHORIZE THE IMPLEMENTATION AND FUNDING OF 100% OF THE COSTS OF A TRANSPORTATION PROJECT, WHICH MAY BE ELIGIBLE FOR FEDERAL-AID/AND/OR STATE AID, OR REIMBURSEMENT FROM BRIDGE NY FUNDS.
WHEREAS, a project for the replacement of BIN 3355520; Oakland Valley Road/CR 49 over Neversink River, Town of Forestburgh, P.I.N. 9755.24 (the "Project") is eligible for funding under Title 23 U.S. Code, as amended, that calls for the apportionment of the costs of such program to be borne at the ratio of 95% Federal funds and 5% non-Federal funds; and
WHEREAS, Resolution 171-22 authorized the Preliminary Engineering/Design work for the Project; and
WHEREAS, the County of Sullivan will design, let and construct the Project; and
WHEREAS, the County of Sullivan desires to advance the Project by making a commitment of 100% of the costs of the work for the Project or portions thereof.
NOW, THEREFORE, BE IT RESOLVED, that the Sullivan County Legislature, duly convened does hereby approve the above-subject Project; and
BE IT FURTHER RESOLVED, that the Sullivan County Legislature hereby authorizes the County of Sullivan to pay 100% of the cost of Preliminary Engineering/Design and Construction, Construction Support, and Construction Inspection work for the Project or portions thereof, with the understanding that qualified costs may be eligible for federal-aid, state-aid, or reimbursement from Bridge NY funds; and
BE IT FURTHER RESOLVED, that the sum of $5...