Narrative of Resolution:
title
Authorize contract modification with Fisher Association for design, engineering and permitting of the second phase of the Callicoon Riverside Park Trail Services.
end
body
If Resolution requires expenditure of County Funds, provide the following information:
Amount to be authorized by Resolution: $100,000
Are funds already budgeted? Yes
If ‘Yes,’ specify appropriation code(s): $100,000 Federal Funding, National Fish and Wildlife Federation; A-7110-230-40-4006
If ‘No,’ specify proposed source of funds: Click or tap here to enter text.
Specify Compliance with Procurement Procedures:
RESOLUTION INTRODUCED BY THE PLANNING AND COMMUNITY RESOURCE COMMITTEE TO AUTHORIZE THE MODIFICATION OF A CONTRACT WITH FISHER ASSOCIATES, P.E., L.S., L.A., D.P.C. FOR THE DESIGN, ENGINEERING AND PERMITTING OF THE SECOND PHASE OF THE CALLICOON RIVERSIDE PARK TRAIL SERVICES
WHEREAS, pursuant to Resolution No. 10-23, Fisher Associates, P.E., L.S., L.A., D.P.C. was awarded a contract in accordance with #R-22-23 for a term of three years with the option of two additional one year extensions, to assist with design engineering and permitting services for existing Sullivan County parks including Lake Superior State Parks, D&H Canal Linear Park and Interpretive Center, Stone Arch Bridge Historical Park, Minisink Battleground Park, Livingston Manor Covered Bridge Park, Fort Delaware Museum of Colonial History, and the Sullivan County Cultural Center (Museum); and
WHEREAS, resolution 249-23 authorized funding for the design and engineering services for hiking trail development at Lake Superior State Park; and
WHEREAS, resolution 308-23 authorized funding for the design, engineering and permitting services related to the development of a 38-acre parcel in the Town of Delaware, located along the Delaware River, in the scope of services; and
WHEREAS, resolution 171-24 authorized funding for the design, engineering and permitting services related to the development of a 38-acre parcel in the Town of Delaware, located along the Delaware River, in the scope of services; and
WHEREAS, resolution 400-24 authorized funding of developing project specific scopes of services for various County-owned and/or operated facilities; and
WHEREAS, resolution 111-25 authorized funding for developing project specific scopes of services, design, engineering and permitting services for various projects within County-owned and/or operated facilities; and
WHEREAS, resolution 288-25 authorized funding to complete design, engineering and permitting services only for D&H Canal Linear Park trail improvements and trail flooding mitigation project; and
WHEREAS, the County wishes to authorize funding for additional services for phase two development of the Callicoon Riverside Park in an amount not to exceed $100,000.00, to be funded by the already received National Fish and Wildlife Foundation (NFWF) grant.
NOW, THEREFORE, BE IT RESOLVED, that the Sullivan County Legislature authorizes the County Manager to execute a modification to the original agreement with Fisher Associates, P.E., L.S., L.A., D.P.C., in a form approved by the County Attorney, to include design, engineering and permitting services related to phase 2 of the Callicoon Riverside Park, 38-acre parcel in the Town of Delaware, located along the Delaware River, in the scope of services; and
BE IT FURTHER RESOLVED, that the Sullivan County Legislature authorizes additional funding to support the agreement with Fischer Associates, P.E., L.S., L.A., D.P.C. in an amount not to exceed $100,000.00 for these additional services, in accordance with the Fee Schedule included in the contract.